6 Works Contracts
4 Completed
2 In Progress
142,620+ Beneficiaries Served

WSDP Works Contracts

Progress of civil works contracts under the Water & Sanitation Development Project.

Boreholes Group 1 100%
#1

Boreholes Group 1

KE-GAWASCO-54759-CW-RFB

Beneficiaries 7,100
Quarter Change 0%
Balance (Kshs) 0

Remarks: Completed

Boreholes Group 2 100%
#2

Boreholes Group 2

KE-GAWASCO-54761-CW-RFB

Beneficiaries 7,800
Quarter Change 0%
Balance (Kshs) 16,810,385.86

Remarks: Completed

Boreholes Group 3 86%
#3

Boreholes Group 3

KE-GAWASCO-54763-CW-RFB

Beneficiaries 17,700
Quarter Change 3%
Balance (Kshs) 4,920,548.26

Remarks: Insecurity. Engaged sub-contractors for 6 tanks (approved).

Dadaab Water Pipeline 100%
#4

Dadaab Water Pipeline

KE-GAWASCO-54771-CW-RFB

Beneficiaries 60,000
Quarter Change 0%
Balance (Kshs) 12,554,925.01

Remarks: Completed

Dadaab Sanitation Facilities 100%
#5

Dadaab Sanitation Facilities

KE-GAWASCO-111742-CW-RFB

Beneficiaries 30,000
Quarter Change 0%
Balance (Kshs) 12,005,121.73

Remarks: Completed

Garissa & Dadaab Office Block 36%
#6

Garissa & Dadaab Office Block

KE-GAWASCO-436012-CW-RFB

Beneficiaries 200 GAWASCO staff & 20 DAWASCO staff
Quarter Change 12%
Balance (Kshs) 41,249,159.03

Remarks: Slow progress

WSDP Consultancy Contracts

Design review, supervision and technical support contracts.

Design Review & Supervision (Part 2)
#1

Design Review & Supervision (Part 2)

Total (Kshs) 367,815,491.55
Paid (Kshs) 254,259,204.30
Balance (Kshs) 113,556,287.00
Q2 2026 Milestones

Joint inspection & handing over to Community/GARUWASCO; Supervision of Office Block; Submitted Monthly Progress reports (April–June 2026)

Remarks: No Objection to Addendum No. 2 issued on 15th June 2026

Design Review & Supervision (Part 1)
#2

Design Review & Supervision (Part 1)

Total (Kshs) 30,078,927.61
Paid (Kshs) 27,424,531.00
Balance (Kshs) 2,654,397.00
Q2 2026 Milestones

Addressed comments and reshared the deliverables

Remarks: Review of deliverables & clearance by MoWSI pending

Pending Goods Contracts

Clean Water Lab Equipment Pending
#1

Clean Water Lab Equipment

KE-GAWASCO-505407-GO-RFQ — Supply, Installation and commissioning of clean water lab equipment and items

Current Status

Initiated Calibration & Accreditation process

Period 10/09/25 — 31/10/25
Paid / Balance 5,858,197.00 / 5,239,697.00
Anticipated Benefit

Improved water monitoring and quality assurance

Remarks: Pending: Training 3 lab technicians, installations, calibration by accredited KEBS company, certification

Pending CLSG II Contracts

Customer Identification Survey Pending
#1

Customer Identification Survey

Consultancy to conduct Customer Identification Survey

Current Status

Started training of enumerators

Period 22nd June 2026 — 21st August 2026
Paid / Balance 0 / 4,250,000.00
Anticipated Benefit

Improve service delivery, NRW management and revenue management

Remarks: Yet to be cleared by WSTF

Key Deliverables — April to June 2026

Major milestones achieved during the second quarter of 2026.

Rehabilitation and Construction of Boreholes Group 1
#1

Rehabilitation and Construction of Boreholes Group 1

Milestone Achieved

End of DLP and issuance of DLP certificate and final payments

Rehabilitation and Construction of Boreholes Group 2
#2

Rehabilitation and Construction of Boreholes Group 2

Milestone Achieved

End of DLP and issuance of DLP certificate

Rehabilitation and Construction of Boreholes Group 3
#3

Rehabilitation and Construction of Boreholes Group 3

Milestone Achieved

Sub-contracted tank sub-contractors for 6 remaining tanks; appointed 4 sub-contractors; signed contracts and started works

Construction of Dadaab town Water supply pipeline works
#4

Construction of Dadaab town Water supply pipeline works

Milestone Achieved

Addressing DLP snag list

Construction of pilot onsite sanitation facilities for Dadaab host communities
#5

Construction of pilot onsite sanitation facilities for Dadaab host communities

Milestone Achieved

Addressing DLP snag list

Construction of Office block in Garissa Town and Admin/Laboratory in Dadaab town
#6

Construction of Office block in Garissa Town and Admin/Laboratory in Dadaab town

Milestone Achieved

Completed superstructure in Dadaab pending septic tank and finishes; Garissa office fixed windows, doors, electrical works

Consultancy — design review and supervision (Time Based Part 2)
#7

Consultancy — design review and supervision (Time Based Part 2)

Milestone Achieved

Joint inspection & monitoring; site handing over to sub-contractors

Consultancy — design review and supervision (Lump Sum Part 1)
#8

Consultancy — design review and supervision (Lump Sum Part 1)

Milestone Achieved

Reshared deliverables with addressed comments

Major Activities — Quarter Ending 30 September 2026

Projected Cumulative IDA Disbursement

Description Amount (Kshs)
Cumulative Disbursement as at 30th June, 2026 1,907,011,345.65
Required Budget for Works 84,216,254.07
Required Budget for Consultancies 116,210,684.00
Required Budget for Goods 5,239,697.00
Required Budget for Operation Costs 30,000,000.00
Projected Cumulative IDA Disbursement by 30th September, 2026 136,775,466.93

Planned Targets by 30 September 2026

# Activity Target
1 Construction of Office block in Garissa Town and Admin/Laboratory in Dadaab town (KE-GAWASCO-436012-CW-RFB) Completed, equipped and occupied
2 Rehabilitation and Construction of Boreholes Group 1 (KE-GAWASCO-54759-CW-RFB) Monitoring — close-out reports
3 Rehabilitation and Construction of Boreholes Group 2 (KE-GAWASCO-54761-CW-RFB) Monitoring — close-out reports
4 Rehabilitation and Construction of Boreholes Group 3 (KE-GAWASCO-54763-CW-RFB) Monitoring — close-out reports
5 Construction of Dadaab town Water supply pipeline works (KE-GAWASCO-54771-CW-RFB) Monitoring — close-out reports
6 Construction of pilot onsite sanitation facilities for Dadaab host communities (KE-GAWASCO-111742-CW-RFB) Monitoring — close-out reports
7 KE-GAWASCO-505407-GO-RFQ — Clean water lab equipment supply & installation Training 3 lab technicians, installations, KEBS calibration & certification; completion of contract
8 Consultancy — design review and supervision (Time Based Part 2) Supervision of office block and monitoring of completed projects DLP; preparation of close-out reports
9 Consultancy — design review and supervision (Lump Sum Part 1) Completion and closure of the consultancy

Projects to be Completed / Commissioned

Works, goods, and consultancy contracts scheduled for completion or commissioning by 30 September 2026.

Boreholes Group 3 Target Q3 2026
#1 Works

Boreholes Group 3

KE-GAWASCO-54763-CW-RFB

Rehabilitation and Construction of Boreholes Group 3 (KE-GAWASCO-54763-CW-RFB)

Target Completion 30 September 2026
Status Scheduled
Garissa & Dadaab Office Block Target Q3 2026
#2 Works

Garissa & Dadaab Office Block

KE-GAWASCO-436012-CW-RFB

Construction of Office block in Garissa Town and Admin/Laboratory in Dadaab town (KE-GAWASCO-436012-CW-RFB)

Target Completion 30 September 2026
Status Scheduled
Clean Water Lab Equipment Target Q3 2026
#3 Goods

Clean Water Lab Equipment

KE-GAWASCO-505407-GO-RFQ

KE-GAWASCO-505407-GO-RFQ — Supply, Installation and commissioning of clean water lab equipment and items

Target Completion 30 September 2026
Status Scheduled
Design Review & Supervision (Part 2) Target Q3 2026
#4 Consultancy

Design Review & Supervision (Part 2)

Consultancy services for design review and supervision — Time Based (Part 2)

Target Completion 30 September 2026
Status Scheduled
Design Review & Supervision (Part 1) Target Q3 2026
#5 Consultancy

Design Review & Supervision (Part 1)

Consultancy services for design review and supervision — Lump Sum (Part 1)

Target Completion 30 September 2026
Status Scheduled

Safeguard Status

# Contract Environmental Status Grievance Register Remarks
1 Rehabilitation and Construction of Boreholes Group 1 (KE-GAWASCO-54759-CW-RFB) ESMP closeout audit prepared and shared with the Bank for review No raised grievances N/A
2 Rehabilitation and Construction of Boreholes Group 2 (KE-GAWASCO-54761-CW-RFB) ESMP closeout audit prepared and shared with the Bank for review No raised grievances N/A
3 Rehabilitation and Construction of Boreholes Group 3 (KE-GAWASCO-54763-CW-RFB) ESMP closeout audit in progress Raised grievance pending resolution Address pending grievance to a logical conclusion
4 Construction of Dadaab town Water supply pipeline works (KE-GAWASCO-54771-CW-RFB) ESMP closeout audit prepared and shared with the Bank for review No raised grievances N/A
5 Construction of pilot onsite sanitation facilities for Dadaab host communities (KE-GAWASCO-111742-CW-RFB) ESMP closeout audit prepared and shared with the Bank for review No raised grievances N/A
6 Construction of Office block in Garissa Town and Admin/Laboratory in Dadaab town (KE-GAWASCO-436012-CW-RFB) Project ESMP in progress No raised grievances — ongoing N/A

Current Project Photos

Site progress photographs from WSDP works as at 30th June 2026.

Boreholes Group 3 — Mathagesi Tank

Mathagesi tank foundation
Mathagesi tank foundation
Mathagesi tower
Mathagesi tower
Mathagesi beams & column
Mathagesi beams & column
Mathagesi tower construction
Mathagesi tower construction

Boreholes Group 3 — Weldoni Tank

Weldoni tank foundation
Weldoni tank foundation
Weldoni tower
Weldoni tower
Weldoni beams & column
Weldoni beams & column
Weldoni tower construction
Weldoni tower construction

Office Block — Garissa & Dadaab

Garissa town office block
Garissa town office block
Dadaab admin/laboratory
Dadaab admin/laboratory
Perimeter wall foundation — Garissa office
Perimeter wall foundation — Garissa office
Window frame fabrication — Dadaab admin/lab
Window frame fabrication — Dadaab admin/lab
Dadaab admin/laboratory
Dadaab admin/laboratory
Dadaab admin/laboratory interior
Dadaab admin/laboratory interior
Dadaab admin/laboratory works
Dadaab admin/laboratory works

Borehole Connections & Monitoring

Borehole 5 individual connection
Borehole 5 individual connection
Borehole 5 individual connection
Borehole 5 individual connection
Yumbis site during monitoring
Yumbis site during monitoring
Yumbis site during monitoring
Yumbis site during monitoring
Yumbis site during monitoring
Yumbis site during monitoring
Welhar during monitoring
Welhar during monitoring
Saretho during monitoring
Saretho during monitoring